Kriegers Flak Grid Connection Cable Routes Cleared of UXO

$
0
0
Danish transmission system operator Energinet.dk, Fugro and subcontractor Boskalis have completed an unexploded ordnance (UXO) survey along the planned cable routes for a grid connecting the 600MW Kriegers Flak wind farm in the Baltic Sea. The survey was carried out in October 2016, Jens Christian Hygebjerg, Energinet.dk’s Chief Project Manager, Project Execution, told Offshore WIND. […]