Offshore construction phase at the 258MW Burbo Bank Extension offshore wind farm is scheduled to start in June 2016, DONG Energy said in a community newsletter. The installation of the export cable, turbine foundations and the offshore substation is set to kick off in June. July is reserved for the installation of the offshore cable array. The first of […]
↧